This Campus Notice is more than 3 years old. Links and contact information may have changed.

Notice from Faculties Management – Power Shutdown - UPDATED REVISED SCHEDULE

Posting Date(s)

As part of our campus high voltage distribution system upgrade project, we will be required to have a number of power interruptions. These power interruptions are necessary to transfer the power from the existing UPEI high voltage electrical switchgear located in the lower level of the Central Utility Building to the new high voltage electrical distribution system located in the new main electrical room recently added on to the Central Utility Building. 

The schedule of power interruptions and associated buildings are listed below. This schedule may be required to be changed as we progress through the stages.  Should that be required, Facilities Management will send out a new campus notice listing the updated schedule.

The emergency power generators will be started for each building prior to the power interruption beginning, which will mean there will be no delay of power for anything currently on emergency power when the power is disconnected.

Facilities Management apologizes for any inconvenience this may cause. If you have any questions or concerns, please contact Jackie MacPhail at jmacphail@upei.ca or 902-566-6034

July 30, 2020 – Beginning at 4:00 pm, expected to take approximately 4 hours to complete.

Faculty of Sustainable Design Engineering Building, Health Sciences Building, Chi-Wan Young Sports Centre, W.A. Murphy Student Centre, SDU Main Building, Steel Building and the Central Utility Building.

August 11, 2020 – Beginning at 4:00 pm, expected to take approximately 12 hours to complete.

Dalton Hall, Memorial Hall, Cass Science Hall, K.C. Irving Chemistry Centre, Bill and Denise Andrew Hall, Don and Marion McDougall Hall, Bernardine Hall, Blanchard Hall, Chaplaincy Centre, Daycare Building, Kelley Memorial Building, Regis and Joan Duffy Research Centre and the Atlantic Veterinary College.

August 13, 2020 – Beginning at 4:00 pm, expected to take approximately 12 hours to complete.

All Campus Buildings